Added Hardware

Follow this procedure when new hardware is added to the system.

Procedure

  1. Validate the SHCD.

    The SHCD defines the topology of a Shasta system, this is needed when generating switch configurations.

    Refer to Validate the SHCD.

  2. Generate the switch configuration file(s).

    Refer to Generate Switch Configs.

  3. Check the differences between the generated configurations and the configurations on the system.

    Refer to Validate Switch Configs.

  4. Run a suite of tests against the management network switches.

    Refer to Network Tests.